Equipment Delivery for Robotic Welding Systems

Release time:2025-05-15     Visits:962

Factory Acceptance Testing

Before equipment leaves the factory it is assembled and run under power. Factory acceptance testing verifies that the robot, positioner, power source, safety system and control logic operate together, and that the first parts produced meet the agreed specification. The customer is invited to witness the test, either on site in Wuxi or by video walkthrough with recorded measurements.

Packing and Protection

Robotic equipment is heavy and precise, so packing is specified rather than improvised.

Packing and shipping approach
RobotSecured on a dedicated steel pallet with axis brakes engaged and transport brackets fitted.
Control cabinetsWooden crate with desiccant, shock indicators and tilt indicators fitted.
Fixtures and toolingDatum faces protected, clamping faces blanked, individually crated where required.
Laser source and opticsProtected from vibration and humidity, shipped in original packaging where available.
DocumentationPacking list, drawings, manuals, calibration records and certificates supplied in a document folder.

Shipping and Documentation

Delivery is normally quoted FOB or CIF depending on the destination. The export documentation set includes commercial invoice, packing list, bill of lading, certificate of origin and, where relevant, CE declaration of conformity. For countries requiring pre-shipment inspection, the inspection is arranged before the container is sealed.

Delivery Schedule and Phasing

Equipment is shipped as a coordinated set rather than item by item. On a turnkey project the cell, the fixtures and the safety system have to arrive in the right order for installation to proceed without waiting, so the shipping plan is built backwards from the agreed installation start date. Where a line is installed in phases, shipment phasing follows the production plan so the customer can begin running the first phase while later equipment is still in transit.

For export destinations, transit time should be confirmed against the carrier schedule before the installation date is fixed. Port congestion and customs clearance are the two variables that most often move an installation date, and neither can be compressed after the fact.

Customs and Import Considerations

Import considerations by destination type
HS classificationConfirmed in advance so the duty rate and any import licence requirement are known before the order is placed.
CertificationCE declaration is supplied as standard. Countries requiring additional local certification need it identified at quotation stage.
Wood packagingISPM 15 heat treatment applied to all solid wood packing, with the marking visible on the crate.
Pre-shipment inspectionWhere the destination requires it, the inspection is arranged before the container is sealed.

Receipt Inspection

On arrival the customer should check the container seal, inspect crates for shock and tilt indicator activation, and verify the packing list against the delivered items. Any transit damage should be recorded on the delivery note and photographed before unpacking, since carrier claims depend on that record.

Packing and shipping arrangements are set by the equipment list, which is drawn from products. The following stage is covered in installation and debugging, and typical shipped configurations appear under robotic welding cells and automatic loading and unloading.

Frequently Asked Questions

Can we witness the factory acceptance test?

Yes. Customers are welcome to attend the FAT in Wuxi, or to review a recorded walkthrough with measurement data if travel is not practical.

What shipping terms do you offer?

FOB and CIF are standard. Other terms such as EXW or DAP can be quoted on request depending on the destination and the customer's freight arrangements.

What export documents are provided?

Commercial invoice, packing list, bill of lading, certificate of origin and the CE declaration where applicable. Additional certification required by the destination country is arranged on request.

What should we do if the equipment arrives damaged?

Record the damage on the delivery note and photograph the crates before unpacking. The shock and tilt indicators provide evidence for the carrier claim, so they should be photographed in place.