Installation goes smoothly when the site is prepared before the equipment arrives. Dade provides a readiness checklist covering floor loading and levelness, the power supply and its protection, compressed air pressure and dryness, shielding gas supply, fume extraction ducting and the safety perimeter. Discovering a power problem after the robot is on site is the most common cause of delay.
A typical robotic welding or cutting cell installation covers the following stages.
| Mechanical installation | Robot mounting, positioner and fixture alignment, safety fencing and light curtains, fume extraction connection. |
|---|---|
| Electrical connection | Power supply, control cabinet wiring, safety circuit integration, earth and bonding verification. |
| Robot commissioning | Mastering, tool centre point calibration, payload and inertia setting, axis limits and safety configuration. |
| Process commissioning | Program loading, weld parameter development per joint, seam tracking calibration, first-off sample approval. |
| Procedure qualification | Where required, WPQ and WPS support under ISO 15614, ASME Section IX or AWS D1.1, arranged with accredited laboratories. |
| Operator training | Programming, daily operation, fault recovery and scheduled maintenance, delivered on the installed cell. |
Commissioning is where the process is proven on the actual part rather than on a sample. Parameters are developed joint by joint: current, voltage, travel speed, wire feed, gas flow and oscillation are tuned against the required penetration and appearance, then locked into the program. Macrosection or visual inspection confirms the result before the cell is released to production.
The cell is handed over against agreed acceptance criteria, normally a defined number of consecutive parts at the target cycle time with the required inspection results. Any deviation is corrected before sign-off rather than left as a punch list item.
Most installation delays trace back to a small number of recurring causes, and all of them are avoidable with preparation before the equipment ships.
| Insufficient power capacity | The welding power source and the robot controller share a supply sized for one of them. Reserve capacity is usually required for weld current peaks. |
|---|---|
| Poor earthing | Inadequate bonding causes arc instability and controller faults that are then misdiagnosed as process problems. |
| Floor not level | A robot bolted to an uneven floor loses positional accuracy across the working envelope and cannot be corrected by programming alone. |
| Compressed air wet or low pressure | Moisture in the air supply causes inconsistent clamping and, on some torches, spatter adhesion. |
| Part not available at commissioning | Parameters cannot be developed against the real part. Production-representative parts must be on site before commissioning starts. |
Commissioning outcomes on comparable installations are documented under customer cases, and the surrounding stages are covered in equipment delivery and technical guidance. The cell families installed are listed under robotic welding.
A single robot welding cell typically takes five to ten working days on site, including parameter development and training. Larger multi-robot lines are scheduled in phases against the production plan.
Dade field engineers perform the installation and commissioning, working alongside the customer's electrical and mechanical team. For export projects, commissioning can be handled by Dade staff or by a partner integrator under Dade supervision.
Operator training covers daily operation, program recall and simple fault recovery. Programmer training covers path teaching and parameter adjustment. Maintenance training covers scheduled servicing and spare parts replacement.
Cycle time is verified during acceptance against the agreed criteria. If it deviates, the cause is identified and corrected before handover, whether it lies in the program, the fixturing or the process parameters.